GREENLAW TOWN HALL OPTIONS APPRAISAL
This is a summary of the up-dated Options Appraisal for Greenlaw Town Hall, which was presented by Paul Jardine of Jura Consultants in a public meeting on Monday 18th June, 2007.
Introduction and Background
The options appraisal has been overseen by a Project Committee. The Committee has an independent Chair (Peter Leggate) and draws its membership from Greenlaw Town Hall Trust and the Friends of Greenlaw. The following multi-disciplinary team was commissioned to undertake the study:
• Jura Consultants • Adam Dudley Architects • Morham and Brotchie Partnership, Quantity Surveyors • David Narro Associates, Structural Engineers • Alba Conservation Trust
The purpose of the options appraisal process is to define a long-term use for the building that is both deliverable and sustainable.
Consultation • 400 questionnaires distributed to Greenlaw households • 122 responses (30.5% of those distributed) • On-line survey to consult a wider audience
PREFERENCE FOR THE FUTURE OF THE TOWN HALL BUILDING Building Future % of Respondents Restoration of the entire building 49.6% Demolition of the entire building 16.8% Partial demolition, leaving the dome and single storey elements 16.0% Restoration of the frontage only with new build behind 10.1% Demolition and relocation and rebuild 5.0% Other 2.5%
PREFERENCE FOR THE FUTURE USE OF GREENLAW TOWN HALL Percentage of Respondents Potential Use Completely in Favour Slightly in Favour No Preference Slightly Against Completely Against Used as a community facility 76.9% 9.3% 2.8% 11.1% 11.3% Converted to a leisure facility 49.5% 26.2% 6.5% 4.7% 13.1% Converted to studios for artists/crafts persons 24.1% 31.5% 15.7% 3.7% 25.0% Converted to offices for sale/lease local business(es) 15.1% 30.2% 10.4% 11.3% 33.0% Converted to serviced visitor/tourist accommodation 8.9% 22.8% 18.8% 14.9% 34.7% Converted to housing for sale 4.8% 4.8% 6.7% 13.5% 70.2% Converted to social housing 4.8% 7.6% 3.8% 9.5% 74.3% Used as a storage for local business(es) on a sale or lease basis 2.9% 6.9% 15.7% 16.7% 57.8% Converted to self catering/ youth hostel 2.0% 11.8% 14.7% 21.6% 50.0% Options Considered
1. Housing (restoration and part new build) 2. Theatre 3. Community Use and Office Space 4. Office (restoration and part new build)
Deliverability Appraisal
Scheme Cost (£) Funding Gap (£) Option 1 – Housing, (restoration) 4,100,000 1,500,000 Option 2 – Housing (new build) 4,300,000 2,550,000 Option 3 – Theatre 3,500,000 2,000,000 Option 4 - Community Use and Office Accommodation 3,500,000 1,800,000 Option 5 – Offices (restoration) 4,200,000 3,400,000 Option 6 – Offices (new build) 4,100,000 3,600,000
Sustainability Appraisal
• Housing o Assumes owner occupation
• Theatre o Require substantial footfall o Greenlaw catchment area is insufficient o Poor long-term prospects
• Offices o Limited local demand o High risk in that achieving significant occupancy is unlikely
• Community Use and Office Space o Income potential o Reasonable level of expenditure o Net operating cost £22,000 per annum
Preferred Option Community Use and Office Space • Funding Gap £1.8 million • Operational Deficit £22,000 • Endowment Required £440,000
|